INTEGRAL IMPROVEMENT OF VICTORIA AERODROME,
ARAUCANIA REGION

Client: Directorate of Airports of the Ministry of Public Works of Chile (MOP).

Date: 2019-2021

Scope: Design of the necessary works to improve the existing infrastructure, focused on the work of extinction of forest fires, includes:

  • New public building for CONAF fire fighter pilots and general aviation.
  • New Aircraft Hangar.
  • New fire water and retardant storage tanks.
  • Wastewater treatment plant and drinking water tanks.
  • Standardization and extension Platform.
  • Runway expansion (extend 300 m and widen to 23 m) and normalization.
  • Parallel shooting with connection to the runway at the ends.
  • Heliport.
  • Parking, interior roads and new access.

Contract Amount: $275 million.

Investment in Works: $7,150 million.

Current status: Finished.